Winter 2017/18

Published: Thursday, 14 December 2017
Star InactiveStar InactiveStar InactiveStar InactiveStar Inactive
 

Chelonian was built in 1994 and is now 23 years old so I thought it was about time it had some tlc to extend its life and improve some of the facilities. These works are being carried out over the winter in a number of stages.

Phase 1 November 2017 

Hull and Fabrication works.

This included zinc coating the hull and several welding jobs to improve the hull life, as well as adding a new skin tank for engine cooling and a new flexiable drive coupling.

Hull zinc

Full details here

Phase 2 January 2018

Exterior painting and internal Joinery

Full details here

Hybrid Upgrade winter/spring 2018

Upgrading the Hybrid system with a new Control Box and a new water cooled motor.

Full details here

Other works

Internal Painting, some woodwork and changes to safety system including fitting a Man Overboard System.

Full details will appear here

Hits: 4032

We use cookies to improve our website and your experience when using it. Cookies used for the essential operation of this site have already been set. To find out more about the cookies we use and how to delete them, see our privacy policy.

  I accept cookies from this site.
EU Cookie Directive plugin by www.channeldigital.co.uk